HomeNewsLocalPolitical Gamble on DM Model Backfires Ahead of NDP12

Political Gamble on DM Model Backfires Ahead of NDP12

Published on

spot_img
spot_img

When the Development Manager model was unveiled in 2023, it was as much a political statement as an infrastructure strategy. The then President Mokgweetsi Masisi government championed it as evidence of its commitment to reforming a sluggish construction sector and jumpstarting the economy ahead of the 2024 general elections. 

The then opposition Umbrella for Democratic Change (UDC), and the Botswana Congress Party (BCP), denounced it as a reckless gamble. A year later, the newly released review vindicates many of those criticisms. 

The Task Team found that costs have surged from P13 billion to P56 billion in just a few years, while many project sites remain idle despite hefty payouts. It warns that cost overruns linked to the DM model could consume up to 60% of the 12th National Development Plan’s budget, crowding out other priorities. 

The report also cites poor project allocation, with Development Managers assigned work outside their competencies, and a lack of transparent criteria for awarding projects. Politically, the findings are an embarrassment for those who sold the model as a quick fix to deep-rooted problems in public works delivery. Instead of a showcase for efficiency, the DM programme has become a symbol of overspending and under-delivery, and a contentious talking point in debates over whether local procurement system is fit for purpose.

Website |  + posts

Latest articles

The $1 Billion De Beers Question

For more than a century, De Beers was synonymous with diamonds. The company that...

Public Servants Panic Over Shrinking Pension Savings

Panic is spreading among Botswana’s public servants after many claimed their monthly pension contributions...

P125 Million Vanishes Into DIS Secrecy

A digital transformation project meant to secure Botswana’s electronic government infrastructure has instead exposed yet...

Manpower Shortages, Ageing Equipment Behind Omang Replacement Delays

Manpower shortages and ageing production equipment are behind the prolonged delays in issuing replacement...

More like this

The $1 Billion De Beers Question

For more than a century, De Beers was synonymous with diamonds. The company that...

Public Servants Panic Over Shrinking Pension Savings

Panic is spreading among Botswana’s public servants after many claimed their monthly pension contributions...

P125 Million Vanishes Into DIS Secrecy

A digital transformation project meant to secure Botswana’s electronic government infrastructure has instead exposed yet...